Capacity Configuration
This article explains how to configure capacity attributes in Agility.
Overview
You can configure the capacity attributes in Team Forecasting. Use the gear icon to access capacity configuration.
Option | Description |
---|---|
Color By: | Displays the team capacity by color type. You can use the Type drop-down to select Color By Asset Status or Asset Type. |
Expanded capacity bar | Toggle to enable or disable the ability to display capacity configuration. This option is disabled by default Note: If you enable this option the capacity bar displays planned capacity and available capacity. |
Capacity as Percentage | Toggle to enable or disable the ability to display capacity as percentage. This option is disabled by default. |
Hide decimal places | If selected, the decimal points are not shown while displaying team capacity. This option is disabled by default. |
Use Team Capacity as : | Select the required capacity option. The available options are Swag or Story Points. |
Swag | If selected, target swag of the team will be compared with the Portfolio item swag. |
Points | If selected, Target estimate points of the team will be compared with the portfolio item estimate points. |
Interval (Columns) | Specify the time period represented in each column. Choose between Weeks, Months, Quarters and Years. This option is used in combination with the Intervals per Column option to determine the length of each columnar period. |
Interval Start | The anchor date for the team. Enter the beginning date of the current period. You won't need to update the Start Date as time moves on. The team forecast is smart enough to understand when the current period starts based on the originally entered Start Date, so this is really a 'set it and forget it' entry. |
Intervals per Column | The number of intervals in a column. Allows you to have intervals of 1 Quarter or 10 Weeks. This option is used in combination with the Interval (Columns) option to determine the length of each columnar period. |
Previous Intervals | It is often helpful to see what was scheduled for at least the last period. Some groups want to understand more of the recent history. This allows you to keep some amount of history visible when using your team forecast by controlling the number of periods to show before the current period. |
Future Intervals | How far out do you want to plan? This sets the number of periods you will see after the current period. |