Member Group Load Trend Report
This article explains how to use the Member load group load trend report in Agility.
Overview
The Member Group Load Trend report shows the amount of work assigned to a member group for the selected sprint over a period of time. The comparison between work in the selected project and other projects gives an indication of the relative allocation of a member group's effort across projects.
By default, the sprint selection range shows the last three sprints and the next one in the schedule.
Accessing This Report
- Click the hamburger menu
> Reports > All Reports. In the Member or Team Reports section, click Member Group Load Trend, or
- Click the hamburger menu
> Sprint > Detail Planning or Member Planning or Detail Tracking or Member Tracking.
Prerequisites
- All Digital.ai Agility trend reports require at least two data points. If not enough data is available, the report may be blank. Depending on the duration you select in the filters, at least one complete period of data must be available to draw a trend line. When selecting days, this means that the minimum duration is actually 2 days, which will include 2 data points.
- Your Show Weekend report settings may affect how much data is selected. For example, if you choose two days as duration and one day is a Saturday or Sunday, and you have elected to not Show Weekends, then you may not have sufficient data to show a trend.
Report Filters or Parameters
- Member Group: Shows data for active members in the selected member group only. When a member is added or removed, both the current and historical values change.
- Start Sprint or Iteration: The first sprint or iteration you want to include in the report.
- End Sprint or Iteration: The last sprint or iteration you want to include in the report.
Technical Details
For Members in the selected Member Group
- Capacity (Selected). Total Capacity for sprints in the selected context.
- Capacity (Other Projects) . Total Capacity outside of the selected context. When sprint schedules do not align, the system allocates Capacity in proportion to the percentage of the time that aligns with each sprint in the current schedule.
To see Capacity (Total) and Capacity (Selected), Capacity Planning must be enabled. If you do not see Capacity values, click the administration icon on the side bar, click System in the Configuration section> System and verify that "Member Capacity" is enabled.
- Detail Estimate (Selected). Total Detail Estimate in the selected context.
- Detail Estimate (Other Projects). Total Detail Estimate outside the selected context. When sprint schedules do not align, the system allocates the Detail Estimate in proportion to the percentage of the time that aligns with each sprint in the current schedule.
- Prior Average (Blue line). A calculated average of Detail Estimate data points across all projects for each sprint prior to the one selected in this report.
Additional Options
- Printing a report
- Saving a report to PDF