This article explains how to use the Test Runs report in Agility.

Overview​

The Test Runs report is a bar graph that shows aggregated project-level test results from an external testing system. This report shows:

  • the number of tests that were not executed
  • the number of tests that passed
  • the number of tests that failed
  • the elapsed time on the test run

Use this report to understand details about projects or releases, sprints or iterations, and testing or quality.

Test Runs report

Accessing This Report​

  1. Click the hamburger menu Hamburger icon > Reports > All Reports.
  2. In the Project or Release Reports or Testing or Quality Reports section, click Test Runs.

Report Filters or Parameters​

Test Suite:

Shows data from the selected test suite.

  • Start Date: The first date the report begins calculating data.

    • For project-based reports, the default start date is the project start date.
    • For sprint or iteration-based reports, the default start date is the sprint or iteration start date.
    • For member-based reports, the default start date is 13 weeks prior to the current date.
    • If the start date is set to the current date or later, no data displays.
  • Duration: The number of days, weeks, or months to display.

    • For project-based reports, the default duration is the number of weeks from the project's start date to today.
    • For sprint or iteration-based reports, the default duration is the number of days in the sprint or iteration.
    • For member-based reports, the default duration is 13 weeks.
    • The report ends at the current date, so if the selected start date and duration extend past the current date, no data displays after the current date.
    • Printing a report
    • Saving a report to PDF