"Where does this number come from?" is one of the most common questions asked of the Agility API, and it usually arrives as a discrepancy: a count on a dashboard does not match the count a query returns, and nobody can say which is wrong.
Usually neither is. They are answering slightly different questions.
The Numbers in the Product Are Queries
The columns and roll-ups you see in Agility are defined as attribute-path expressions — the same syntax described in the query grammar, available to you through the API. A "done count" on a board is something close to:
Timebox.Workitems:PrimaryWorkitem[EffectiveAssetState='Closed';Scope=$Scope;Team=$Team].@Count
That is a downcast, an inline filter with three terms, a filter-context variable and an aggregation — nothing you cannot write yourself. So reproducing a reported figure is not guesswork; it is a matter of matching the expression, and the mismatches almost always come down to a small number of recurring causes.
Start with the State Attribute
The most common cause of a mismatch is using the wrong state attribute. There are
two, both read-only and both of type State:
| Attribute | What it reflects |
|---|---|
AssetState | The asset's own lifecycle — active, closed, deleted |
EffectiveAssetState | AssetState or the rollup of the item's workflow status |
EffectiveAssetState is a calculated attribute, and the rule is a
substitution rather than a simple OR:
EffectiveAssetState =
AssetState = Active -> Status#.RollupState, or Future when that is null
otherwise -> AssetState
In words: while an item is Active, its workflow status replaces its state
entirely. Once it is anything else — Future, Closed, Dead, Deleted — its own
AssetState stands and the status is ignored.
The practical case everyone meets first is a Story sitting in a "Done" or
"Accepted" column. Its AssetState is still Active — nothing closed it as an
asset — but its status rolls up as closed, so the product counts it as complete.
Filter on AssetState='Closed' and you miss every one of them.
Future, not ActiveThe null fallback is easy to miss and it is not intuitive. If an item is Active
and has no Status assigned, its RollupState is null and
EffectiveAssetState becomes Future.
So a freshly created, unstarted work item is effectively Future. A filter of
EffectiveAssetState='Active' will not return it, and a count of "not yet
started" built on AssetState will disagree with one built on
EffectiveAssetState for exactly these items.
The calculation reads Status#.RollupState — note the
# now-only operator. It resolves the
status's rollup as it is currently, not as it was at the moment being
examined.
That matters whenever you filter history on EffectiveAssetState. If a status
was later reconfigured to roll up differently, historical rows are evaluated
against the new rollup, so a replay of past transitions can shift under you
without any work item having changed.
If you need the rollup as it stood at the time, select Status.RollupState
without the # and compare it yourself.
Two further consequences worth knowing:
- Status names do not matter; rollups do. Two instances can use identical
status names and still report differently. When a count is wrong on one
instance only, compare
Status.RollupState, notStatus.Name. - The calculation can be switched off. A
SuppressEffectiveStateCalculationsetting makesEffectiveAssetStatereturn plainAssetState. It is per-instance, so a query that reconciles on one deployment can disagree on another with no change to the data.
The product's own reports use EffectiveAssetState in most places where you
would reach for AssetState. If your count is close but consistently low, this
is almost certainly why.
!= on a state attribute is not a negationBoth are State-typed, so EffectiveAssetState!='Closed' compiles to
< 128 — it excludes Dead and Deleted items as well as Closed ones. It means
"before Closed", not "not Closed".
That is usually what a report wants, which is why it is easy to copy without noticing. See State attributes.
"Inactive" and "Closed" Are the Same Thing
The vocabulary is genuinely inconsistent here, and it trips people up in both
directions — looking for a Close operation that does not exist, or expecting an
Inactive state that does not either.
The operation is almost always Inactivate. The resulting state is Closed.
Counted across a live instance's metadata:
| Operation | Asset types | Notes |
|---|---|---|
Inactivate | 72 | Effectively everything — Story, Defect, Epic, Issue, Goal, and every list type |
Close | 1 | Timebox only |
QuickClose | 4 | Defect, Story, Task, Test — closes without the usual workflow steps |
Reactivate | 25 | The inverse of Inactivate |
No asset type offers both Inactivate and Close. So if you are closing a
Timebox you invoke Close; for anything else you invoke Inactivate — and in
both cases the asset ends up with an AssetState of Closed.
There is no Inactive value in the state model at all. AssetState runs
Future, Active, Closed, Dead, Deleted; "inactive" is only ever the name
of the verb.
Filter on the state, not the operation name. AssetState='Closed' and
EffectiveAssetState='Closed' are the right predicates regardless of which
operation put the asset there.
Where "inactive" does appear as an attribute — IsInactive on some types — treat
it as a separate boolean flag and check meta.v1 for what the type actually
exposes rather than assuming it mirrors AssetState.
Inactivate results in AssetState of Closed — see
operations.
The Date Attributes Are Not Interchangeable
DoneDate, ClosedDate and RetireDate are all read-only dates, and they do not
mean the same thing. Filtering on the wrong one gives a plausible number that
drifts from the report.
Before assuming which one a figure uses, check the type in
meta.v1 and try the alternatives — a discrepancy that changes
when you swap the date attribute has found its own cause.
And if the figure is bucketed by sprint, iteration or any other range, check the
boundary convention before anything else: EndDate is exclusive, stored as
midnight of the day after the range ends, so a filter of EndDate<= the date
shown in the UI silently drops a period. See
Dates and date ranges.
Worked Example: Velocity by Date
Counting the items completed in each of a series of intervals looks simple:
{
"from": "PrimaryWorkitem",
"select": ["Name", "Status.Name", "EffectiveAssetState", "DoneDate"],
"filter": [
"AssetState!='Dead';EffectiveAssetState='Closed';Scope[AssetState!='Closed'];Scope.ParentMeAndUp=$ScopeRoot;DoneDate>=$StartDate;DoneDate<=$EndDate"
],
"with": {
"$ScopeRoot": "Scope:1234",
"$StartDate": "2020-01-02T00:00:00",
"$EndDate": "2020-01-09T00:00:00"
},
"page": { "size": 1000, "start": 0 }
}
Three things in that filter are worth noticing, because they recur in every report-reproduction query:
Scope[AssetState!='Closed']— an inline filter on the relation, excluding items in closed projects. Reports almost always do this; hand-written queries almost always forget it.Scope.ParentMeAndUp=$ScopeRoot— matches the whole project subtree, not just direct children.- A filter-context variable for each bound, so the same query shape can be reissued per interval without rebuilding the string.
Run it once per interval and you have a velocity series.
DoneDate filter will not tell youThis is the discrepancy that sends people to support.
DoneDate reflects the item's current completion, so a "done in this week"
count built on it silently omits an item that was completed that week and later
reopened — and it includes an item completed earlier and re-completed since,
depending on how the date is maintained.
A report that counts completions as they happened must read the transitions, not the current value.
Worked Example: Effort and Hours Worked
Effort is not an attribute you can select on a workitem directly — it is the
sum of the Actual records logged against it. Each time a team member
records time, the system creates an Actual carrying Value, Date,
Member, Workitem and Scope (required).
Actuals usually go on Tasks. To total a Story's actuals, including its Tasks,
select ChildrenMeAndDown.Actuals.Value.@Sum.
Actuals recorded against a single workitem — bounded by the workitem's own key:
{
"from": "Actual",
"where": { "Workitem": "Task:1217" },
"select": ["Date", "Value", "Member.Name"],
"page": { "size": 100, "start": 0 }
}
Hours worked by member, within a date range — sum Value per Member,
using filter-context variables for the bound, the same pattern as the
velocity example above:
{
"from": "Member",
"select": ["Name", "Actuals[Date>=$StartDate;Date<$EndDate].Value.@Sum"],
"with": { "$StartDate": "2026-08-01", "$EndDate": "2026-09-01" },
"page": { "size": 50, "start": 0 }
}
Progress on an Epic — the same downcast idiom from
Relations, applied
to Estimate instead of a count, gives closed vs. total estimate for
everything under an Epic. Bounded by the Epic's own key, so no page is
required:
{
"from": "Epic",
"where": { "ID": "Epic:1207" },
"select": [
"Name",
"SubsAndDown:PrimaryWorkitem[EffectiveAssetState='Closed'].Estimate.@Sum",
"SubsAndDown:PrimaryWorkitem[AssetState!='Dead'].Estimate.@Sum"
]
}
Divide the two sums for a percent-complete figure.
Counting Transitions Instead of Current State
History is queryable as a relation, and Prior
gives you the value immediately before each change. A state transition is
therefore expressible directly:
Prior.EffectiveAssetState!='Closed';EffectiveAssetState='Closed'
That is "became done". Reverse it for "became not done":
Prior.EffectiveAssetState='Closed';EffectiveAssetState!='Closed'
Select both sides of every relevant change, ordered, and you can replay an item's completion history rather than inferring it:
{
"from": "History",
"select": ["Prior.EffectiveAssetState", "EffectiveAssetState", "ChangeDate"],
"filter": "ChangeDate<=$AsofDate;((Prior.EffectiveAssetState!='Closed';EffectiveAssetState='Closed')|(Prior.EffectiveAssetState='Closed';EffectiveAssetState!='Closed'))",
"sort": ["+ChangeDate"]
}
Note the grouping: (A;B)|(C;D) — ; is AND, | is OR, and parentheses group.
See boolean operators.
Process the changes in order. An item that was completed, reopened and completed again produces three rows, and only the last one determines whether it counts as done at the end of the period. Taking the first match, or counting rows, gives the wrong answer for exactly the items that caused the question.
Reconstructing an as-of-Date View
The same idea answers "what did this look like on a date in the past" without
asof:
History[Scope=$ScopeContext;EffectiveAssetState='Closed';ChangeDate<=$AsofDate;(RetireDate>=$AsofDate|-RetireDate)]
Read that as: a version existed, in this scope, that was Closed, changed on or
before the date, and either had not retired by then or never retired at all. The
-RetireDate term is a unary existence
assertion — "has no RetireDate".
Compare with asof,
which asks the server for the state at a moment. asof is simpler; the history
filter is more flexible when the condition itself involves change.
A Checklist for Chasing a Discrepancy
When a reported figure and a query disagree, work through these in order:
- Is the report using
EffectiveAssetStatewhere you usedAssetState? - Does the report exclude items in closed or dead projects?
- Does it scope to a subtree (
ParentMeAndUp) rather than direct children? - Is it counting current state, or transitions during the period?
- Are you filtering on the same date attribute?
- Is your query paged, and are you reading every page? A count that stops at the first page is a common and silent error.
Related
-
Product reports this guide reproduces: the Velocity reports, and the Velocity by Date report — the worked example's product counterpart; Cumulative Flow by Status — the report the transition-counting section approximates.
-
Moments and history — the
History,PriorandNowrelations -
Filter expressions — grouping, unary existence, state comparison
-
Query size and performance — paging these queries safely