Agile Earned Value by Date

The Agile Earned Value by Date dataset offers an in-depth view of project performance by tracking earned value metrics over time. It helps project managers and teams assess progress, forecast future outcomes, and identify potential issues by comparing planned and actual performance at various stages of the project. This dataset is essential for monitoring project health, managing costs, and ensuring the project remains aligned with its objectives.

note

In the parent portfolio item hierarchy, the topmost parent portfolio item must have been closed within the last 13 months. Any top portfolio item closed beyond the entitlement period will be excluded.

The following are the components of this dataset:

Attribute NameDescription
Calendar dateGregorian calendar date displayed in the format 'M/D/YYYY'
Calendar weekGregorian calendar week displaying the week number. For example,
W21, W22.
Lagging count of weeksCount of defects for the current week and the preceding two
Last refresh display dateDate of the most recent update or refresh of data in a dataset. It is in date, time, and time zone format.
Sys_sourceUnique identifier for the source
Work item backlog groupBacklog group of the work item
Work item iterationIteration of the work item
Work item planning levelPlanning level of the work item
Work item portfolio itemPortfolio item of the work item
Work item teamTeam of the work item
Metric NameDescription
Completed story pointsThe total amount of planning level work completed at the end of each iteration.
Completed work itemsThe total amount of planning level work completed at the end of each iteration.
Total story pointsSummation of story points associated with all work items within a planning level.
Work item countCount of work items in an iteration.