Agile Earned Value by Date
The Agile Earned Value by Date dataset offers an in-depth view of project performance by tracking earned value metrics over time. It helps project managers and teams assess progress, forecast future outcomes, and identify potential issues by comparing planned and actual performance at various stages of the project. This dataset is essential for monitoring project health, managing costs, and ensuring the project remains aligned with its objectives.
note
In the parent portfolio item hierarchy, the topmost parent portfolio item must have been closed within the last 13 months. Any top portfolio item closed beyond the entitlement period will be excluded.
The following are the components of this dataset:
Attribute Name | Description |
---|---|
Calendar date | Gregorian calendar date displayed in the format 'M/D/YYYY' |
Calendar week | Gregorian calendar week displaying the week number. For example, |
W21, W22. | |
Lagging count of weeks | Count of defects for the current week and the preceding two |
Last refresh display date | Date of the most recent update or refresh of data in a dataset. It is in date, time, and time zone format. |
Sys_source | Unique identifier for the source |
Work item backlog group | Backlog group of the work item |
Work item iteration | Iteration of the work item |
Work item planning level | Planning level of the work item |
Work item portfolio item | Portfolio item of the work item |
Work item team | Team of the work item |
Metric Name | Description |
---|---|
Completed story points | The total amount of planning level work completed at the end of each iteration. |
Completed work items | The total amount of planning level work completed at the end of each iteration. |
Total story points | Summation of story points associated with all work items within a planning level. |
Work item count | Count of work items in an iteration. |