Assigning Workitems to a Team on the Team Scheduling Page

This topic explains how to assign Workitems to a Team on the Team Scheduling Page.

Overview

Follow these steps to assign (or schedule) backlog items to a team on the Team Scheduling page.

Steps

Simply drag-and-drop any backlog item directly to a team.

  1. Click the hamburger menu Hamburger icon Release > Team Scheduling.

  2. If not already selected, select a project from the project navigator.

  3. Locate the desired project or release, and click the Teams tab.

  4. Select an item in the backlog grid on the right, and then drag it to a team on the left.

    • You can assign items to both a project or release and a team at same time
    • You an drag a portfolio item onto a team to assign the target team or to assign the team to any child items that exist.

Release Unscheduled work

If a portfolio item contains any child workitems that are assigned to other projects or releases, the system lists them and asks if you want move (or unite) them to the same project as the parent portfolio item:

  • Click Yes, Unite These Workitems to assign the workitems to the same project.
  • Click No, Leave Them There to leave them in their current project(s).
  • Click Show what has already been moved to view the work items that have already been moved to a project.