Work Item Snapshot Weekly

The Work item snapshot weekly dataset provides a detailed weekly summary of work item statuses and metrics. This dataset is crucial for tracking progress, identifying bottlenecks, and ensuring alignment with project timelines and objectives. It includes key metrics such as the number of work items created, completed, and in progress, as well as the distribution of work items across different categories and teams. By offering a comprehensive and timely snapshot of work item trends, this dataset aids teams in maintaining productivity and ensuring effective project management.

note

The data is filtered to include only the snapshot dates from the last 24 weeks.

The following are the components of this dataset:

Attribute NameDescription
Calendar dateGregorian calendar date displayed in the format 'M/D/YYYY'
Calendar weekGregorian calendar week displaying the week number. For example,
W21, W22.
Last refresh display dateDate of the most recent update or refresh of data in a dataset. It is in date, time, and time zone format.
Sys_sourceUnique identifier for the source
Work itemUnique identifier for the work item
Work item backlog groupBacklog group of the work item
Work item iterationIteration of the work item
Work item planning levelPlanning level of the work item
Work item portfolio itemPortfolio item of the work item
Work item priorityPriority of the work item
Work item stateCurrent state of the work item
Work item status sourceCurrent status of the source work item
Work item teamTeam of the work item
Work item typeType of the work item
Metric NameDescription
Completed story pointsThe total story points are completed at the end of each iteration
Completed work itemsThe total amount of work items at the end of each iteration
Detail estimate hoursSummation of all estimate points of the backlog item in the iteration
Open story pointsThe total number of story points associated with work items that are currently in an "Open" or "To Do" state within a project or planning level
Open work itemsThe total number of work items that are currently in an "Open" or "To Do" state within a project or planning level
To do hoursEstimated time required to complete pending tasks associated with a work item
Total story pointsSummation of story points associated with all work items within a planning level
Work item countCount of work items in an iteration