Velocity by Date Report

The Velocity by Date report is a bar chart that:

  • shows the total Estimate completed, by Date, over a specified date range (days, weeks, or months).
  • rolls up velocity across different sprint schedules.

Velocity_by_date

Accessing This Report

  1. Click the hamburger menu Hamburger iconReportsAll Reports.
  2. In the Project or Release Reports section or Planning Reports section, click Velocity by Date.

Report Filters or Parameters

  • Team: Shows Team-specific data for the project or program. The default value is "All" or "Blank".

  • Backlog Group: Shows data assigned to the selected backlog group.

  • Workitem: Shows data for a specific work item type: All (all workitems), Stories, Defects, or Testsets. The default option is "All".

  • Aggregation Type: Determines how the data is aggregated. Valid values are:

    • Sum of Estimate - Sum of the Estimate values.
    • Workitem Count - Count of work items regardless of estimate value.
  • Portfolio Item: Shows work items in the selected portfolio item and all of it's children. The default option is "Blank" and shows all work items.

  • Start Date: The first date the report begins calculating data.

    • For project-based reports, the default start date is the project start date.
    • For sprint or iteration-based reports, the default start date is the sprint or iteration start date.
    • For member-based reports, the default start date is 13 weeks prior to the current date.
    • If the start date is set to the current date or later, no data displays.
  • Interval: The length of each interval (days, weeks, or months) you want to show in the report. By default the length+gap as set on the project's sprint schedule. If no schedule is available, it defaults to 2 weeks.

    • For projects, the report uses the number of weeks from the project's start date to today.
    • For sprints, report uses the the number of days in the sprint.
  • Grouping: Shows the velocity report of the selected grouping.

​Technical Details

  • By default, the date range is set to the beginning and ending dates of the project and the duration is set to measure by weeks.
  • If the project has no end date, the end date defaults to the current date.
  • The report considers the work items "Date Completed" attribute when assigning the work item to a period.